On Saturday, April 6th 5:30-10 am In order to accommodate the addition of HVAC units on the second-floor lab space renovation project in the east end of the building. Air Handling units 3 and 4 will be shutdown thus affecting supply airflow to all floors on the east side of the building. During this time […]
Category: Outages
Jeffrey T. Fort Neuroscience Research Building-Air Handling Unit 3/29/2024
On Friday, March 29th 3-7 am. Due to the construction fit out project on the west end of the 10th floor there will be limited air flow and slight temperature changes throughout the whole 10th floor. We do not foresee major temperature changes in the holding rooms. Thank you for your patience while we finish […]
McDonnell Medical Sciences Building-Chilled Water Service Interruption 3/27/2024
On March 27th from 3 am to 8 am there will be a chilled water outage for the 7th floor of the McDonnell Medical Sciences building. In this time there will be partial to no cooling for the 7th floor of the building.
Renard Hospital-Electric Service Interruption 4/13/2024
On Saturday, April 13th 5 am – 1 pm National Electric Co. will be replacing the ATS (Automatic Transfer Switch) for the Emergency power in the bldg. The outage will affect all the emergency power and lighting, some fire alarm components, air handlers and Elevators. However normal power (Receptacles, lighting) will not be affected.
McDonnell Pediatric Research Building-Air Handling Unit Service Interruption 3/27/2024
On Wednesday, March 27th 5-8 am Facilities will turn off the air handler serving the pedestrian link and administration offices for the south section of the building for maintenance. The pedestrian link along with the administration offices located on floors 3 through 11 will experience loss of airflow and cooler-than-normal temperatures during time.
McDonnell Pediatric Research Building-DI Water Service Interruption 3/26/2024
On Tuesday, March 26th 5-8 am there will be no DI Water available for use on the 10th floor. This will affect all lab sink faucets and any Millipore systems utilizing DI Water.
CSRB North Tower Addition-431/441 ABSL3 Suite Service Interruption 4/2/2024
On Tuesday, April 2nd 6 am – 6 pm Johnson Controls will be replacing the network control engine that serves 431/441 ABSL3 suite. NO work may occur in the 431/441 ABSL3 suite during this outage. Other ABSL3 suites in the 4th floor biohazard area will be available during this outage.
CSRB North Tower Addition-Exhaust Fan Service Interruption 3/21/2024
On Thursday, March 21st 4-6 am to perform preventative maintenance task on the HVAC systems serving the 4th and 5th floor facilities technicians will be shutting down supply and exhaust fans serving the areas. During this time occupants of the non BSL3 labs on the 4th floor and the 5th floor may experience a reduction […]
McDonnell Medical Sciences Building-Vacuum Service Interruption 3/21/2024
On March 21st from 3 am to 7 am there will be a lab air and vacuum outage for the McDonnell Medical Sciences building for the 7th floor construction. There will be limited to no vacuum and lab air to the 7th floor in this time frame.
Clayton Garage-Fire Alarm System Service Interruption 3/18-19/2024