On Saturday, March 8th, 7-11 am, facilities and contractors will conduct electrical switchgear maintenance for floors 6 through 8; standard power will be de-energized; however, emergency power will be available during the outage. This means that all emergency outlets (RED) will be restored once the generator starts up. The affected devices are as follows: receptacles, […]
Category: Outages
Steven & Susan Lipstein BJC Institute of Health-Electric Service Interruption 2/25/2025
During the time and date above facilities along with contractors will be conducting an outage to upgrade stand-alone AHU on the 7th fl. from normal power to emergency power. The affected rooms are as follows: 0711-1, 0711-2, 0713, 0715, 0716, 0717, 0718.
CSRB North Tower Addition-Electric Service Interruption 3/6/2025
On Thursday, March 6th, from 4-6 am, the emergency lighting circuit for the NTA elevator lobbies will be shut off to reconnect the 7FL new emergency lighting and disconnect the 10FL emergency lighting for replacement.
CSRB North Tower Addition-Electric Service Interruption 2/20/2025
On Thursday, February 20th from 4-6 am, the emergency lighting circuit for the NTA elevator lobbies will be shut off to reconnect the 4FL new emergency lighting and disconnect 7FL emergency lighting. This emergency circuit impacts BSL-3 lab lighting on the 4FL. NO work may occur in the 4th floor biohazard area during this outage.
CSRB North Tower Addition-Electric Service Interruption 3/6/2025
On Thursday, March 6th from 4-6 am, the emergency lighting circuit for the NTA elevator lobbies will be shut off to reconnect the 7FL new emergency lighting and disconnect the 10FL emergency lighting for replacement.
McMillan Hospital-Air Handling Unit Service Interruption 2/13/2025
On Thursday, February 13th, from 4-6 am, facilities technicians will be performing preventative maintenance on the HVAC system serving BSL3 lab MCM1103. During this time NO work shall take place in the BSL3 suite 1103.
McDonnell Pediatric Research Building-Supply Air Handler Service Interruption 2/13/2025
On Thursday, February 13th, 4-7 am, facilities technicians will be troubleshooting and making repairs to the air handling unit (AHU-1) that serves the BSL3 lab suites 8201, 8210, 7303, 7302, and 7230 in the building. During this time NO work shall be conducted in the BSL3 lab suites 8201, 8210, 7303, 7302, and 7230.
McDonnell Medical Sciences Building-Exhaust Fan Service Interruption 2/12/2025
On Wednesday, February 12th, from 6 am to 2 pm, exhaust fan 18 will be shut down to facilitate the construction of the 9th-floor renovation project and ensure the safety of the electrical technicians changing the electrical feeds and control wiring. The areas affected are the 9th and 7th-floor labs and equipment that use exhaust […]
East Building-Elevator Service Interruption 2/17/2025
On Monday, February 17th, 2-6 am, as part of the modernization project, both elevators (#47 & #48) will be removed from service to allow contractors to perform work in the elevator shaft safely. Elevator #48 will be returned to service by 6 am.
CSRB North Tower Addition-Domestic Cold Water Service Interruption 2/12/2025
On Wednesday, February 12th 4-6 am, the domestic cold water to the 4th floor will be shut off during the outage to accommodate tying in a new water cooler in the 4th floor elevator lobby area. No domestic cold water will be available to restrooms (faucets, urinals, toilets), showers, and service sinks on the 4th […]