Elevators in these buildings will be out of service for about 2 to 4 hours between 7:00 am and 3:30 pm starting on Monday, March 27- Wednesday, March 29 to conduct annual inspections and fire recall tests, as required by the Elevator Safety Unit of the Missouri Department of Public Safety. The elevators will be […]
Category: Outages
Canceled-4444 Forest Park Avenue-Electric Service Interruption 3/26/2023
On Sunday, March 26th 7 am – 11 am the 2nd outage for 4444 Forest Park. The purpose of this outage is to perform maintenance and testing on the major components of the main electrical switchgear, which distributes power throughout the 4444-Forest Park Building. To do this, Facilities Electricians will switch between the two utilities, […]
Clinical Sciences Research Building-7th Floor Hot Water Service Interruption 3/4/2023
On Saturday, March 4th 2 am – 2 pm contractors will be making necessary repairs to the heating hot water system for the seventh floor. The entire seventh floor may experience slightly cooler than normal temperatures during this time.
Cancer Research Building-Electric Service Interruption 3/4/2023
On Saturday, March 4th from 9 am to 10 am there will be an electrical outage to two panels in the Cancer Research Building. One affects the 3rd floor 3600 suite only and the other only affects the 5th floor room 5520. In this time frame there will be no power to the outlets serving […]
Steven & Susan Lipstein BJC Institute of Health-Air Handling Unit Service Interruption 3/8/2023
On Wednesday, March 8th 2 am – 8 am OFMD will be completing preventative maintenance on the supply and exhaust air handling units that serve the basement vivarium including the B120 ABSL3 suite. In addition, duct tie-ins will be completed by the Vertical Expansion contractors during the outage. The supply and exhaust air handling units […]
Clinical Sciences Research Building-Air Handling Unit Service Interruption 3/1/2023-3/2/2023
Facilities will be turning off the air handler that feeds the north side of the fourth floor. The unit will be off periodically from Wednesday, March 1st 7:00 pm to Thursday, March 2nd 5:00 am. During this time the north side of the fourth floor may notice a decrease in airflow and slightly warmer than […]
Clinical Sciences Research Building-Air Handling Unit Service Interruption 2/28/2023-3/1/2023
Facilities will be turning off the air handler that feeds the south side of the third floor. The unit will be off periodically from Tuesday, February 28th 5:00 pm to Wednesday, March 1st 3:00 am. During this time the south side of the third floor may notice a decrease in airflow and slightly warmer than […]
Clinical Sciences Research Building-Air Handling Unit 2/27/2023-2/28/2023
Facilities will be turning off the air handler that feeds the north side of the third floor. The unit will be off periodically on February 27th 5:00 pm Monday night to February 28th 3:00 am Tuesday morning. During this time the north side of the third floor may notice a decrease in airflow and slightly […]
McDonnell Medical Sciences Building-Building Automation Systems Service Interruption 2/28/2023
On Tuesday, February 28th from 6 am to 10 am there will be an outage to the building automation systems for the south side of the 8th floor for the McDonnell Medical Sciences building. In this time frame there will be loss of communication to equipment serving supply air and exhaust air to the south […]
McDonnell Pediatric Research Building-Lab 8201 BSL3 Services Interruption 3/2/2023