The purpose of this outage is to perform maintenance and testing on the ‘D’ feed portion of the McKinley Substation switchgear. Facilities electricians will perform switching in all affected buildings, to isolate and de-energize the ‘D’ feed. Facilities electricians and Service Contractors will inspect and test the breakers, relays, and major components of the de-energized […]
Category: Outages
Southwest Tower-DI Water Service Interruption 4/8-13/2024
The 7th-floor DI water system has failed and will need to be repaired. Facilities will order parts and make necessary repairs. DI water is available on floors 6 and 8. The outage will be updated when the parts have arrived and installed.
McDonnell Pediatric Research Building-Hot Water Service Interruption 4/16/2024
On Tuesday, April 16th 6 am – 2pm in support of the construction project on the 10th floor, the heating hot water will be shut down for the 10th floor only. During this outage, the 10th floor may experience cooler than normal temperatures and will not have any negative affect to the air handlers, fume […]
McDonnell Pediatric Research Building-Plumbing System in BSL3 lab 8201C Service Interruption 4/3-4/4/2024
Starting Wednesday, April 3rd at 10 pm and continuing through 9:30 am Thursday, April 4th BSL3 lab 8201C will be out of service so Facilities Technicians can make repairs to the plumbing system serving the sink. During this time work may take place in other spaces of the lab suite but NO work shall occur […]
East Building-Chilled Water Service Interruption 4/13/2024
On April 13th from 4 am to 2 pm, there will be a chilled water outage for the East Building that will affect partial areas on the first floor. In this time, there will be limited to no cooling and air flow for the Cyclotron office, PET bay, scan rooms, and the MRI Bay all […]
CSRB North Tower Addition-Elevator Service Interruption 4/23-4/24/2024
The NTA elevators will be taken out of service, one at a time as needed, between 7 am and 4 pm, on Tuesday, April 23rd & Wednesday, April 24th. This will allow contractors to install new fire alarm devices in the elevator machine rooms, and in the top of the elevator hoist ways. This is […]
CSRB North Tower Addition-Elevator Service Interruption 4/17/2024
The NTA elevators will be taken out of service, one at a time as needed, between 7am and 4pm on Wednesday, April 17th. This will allow contractors to install new fire alarm devices in the elevator pits and basement as part of the fire alarm upgrade project.
West Building-Air Handling Unit Service Interruption 4/6/2024
On Saturday, April 6th contractors will be working on the air handler that serves Lab 1754. The lab will have no airflow and may be warmer than normal during this time.
Steven & Susan Lipstein BJC Institute of Health-Vacuum Service Interruption 4/12-4/13/2024
Contractors will be turning off the vacuum system that serves the lower level along with floors 7-11. No vacuum will be available during this time. This outage will begin on Saturday, April 12th at 7:00 am and run through Sunday, April 13th at 6:00 pm.
McDonnell Pediatric Research Building-Air Handling Unit Service Interruption 4/15/2024-5/11/2024
Between April 15th – May 11th contractors will be cleaning the supply duct work serving the 9th floor labs nightly starting at 8 pm and will be completed by 6 am. Occupants in the space during those times should expect to see tradespeople , equipment in the lab hallways, a change in airflow noise, and […]