From May 21st until May 27th, contractors will be working on the exhaust pipes of the BJC-IOH generators and the Wohl Hospital generator exhaust. Each day, from 7 am until 3:30 pm, the generators will be inoperable. However, they will be closely monitored. In the event of a NORMAL power loss to either building, we’ll […]
News
Gary C. Werths Siteman Cancer Center-Fire Alarm Service Interruption 6/1/2025
Starting Sunday, June 1st, 7 am- 3:30 pm, facilities and contractors will perform tests on the fire alarm’s duct detector system during the above times. No alarms or strobes will be heard or seen during these tests.
Jeffrey T. Fort Neuroscience Research Building-Air Handling Unit Service Interruption 5/16/2025
On Friday, May 16th, 8 am – 1 pm, contractors will replacing a valve on the building’s heat system. During this outage, the building will experience some temperature fluctuations.
Jeffrey T. Fort Neuroscience Research Building-Steam Service Interruption 5/15/2025
Due to upgrades being made to the building, no heat will be generated on Thursday, May 15th, 6 am-12 pm. Outside temperatures and system adjustments should make temperature changes minimal. We will be monitoring temperatures in critical areas as well. Autoclaves and cage wash will not be affected by this outage.
McDonnell Pediatric Research Building-7303 BSL3 Suite Service Interruption 5/15/2025
On Thursday, May 15th, 9-9:30 am, the access programming for the 7303 BSL3 suite will be updated. NO work may occur in the 7303 BSL3 suite during this outage.
East McDonnell Repairs and Cleaning of Facade On Hold
The East McDonnell Repairs and Facade Cleaning Project has been placed on hold. We will let you know when it resumes. If you have any questions, please contact James Wade, Project Coordinator I.
St. Louis Children’s Hospital (SLCH) Construction Updates
Sent on behalf of Barnes-Jewish Hospital. At any given time, dozens of construction projects are taking place throughout the St. Louis Children’s Hospital and campus—some you see, many you don’t. Renovations, upgrades and new construction are needed to accommodate new technology, enable departments to operate more efficiently, and, most importantly, create the most comfortable environment […]
May 12th: Chick-fil-a Remodel on the University of Health Sciences & Pharmacy in St. Louis (UHSP) Campus
Sent on behalf of the University of Health Sciences & Pharmacy in St. Louis. Starting May 12th, the Chick-fil-A location on the University of Health Sciences and Pharmacy campus will be closed for renovations. Construction will last approximately four weeks, with Chick-fil-A scheduled to reopen on June 12th.During the Chick-fil-A closure, the on-campus Starbucks location […]
May 12th: Steven & Susan Lipstein BJC Institute of Health (BJCIH) to Clinical Sciences Research Building (CSRB) Link Carpet Replacement
The BJCIH to CSRB Link Carpet Replacement Project will start on May 12th. The project will be completed by May 22nd, with all final cleaning, trash, and equipment removed from the site (including the contractor-provided dumpster). The work will be done after hours, starting at 6 pm, Monday through Friday. Each phase will be done […]
May 12-14: Lift at the Mid Campus Center (MCC)
Fixture Contracting has a lift scheduled for delivery on May 12th for two days to install glass on the second floor south elevation of the MCC, weather permitting. If you have any questions, please contact James Wade, Project Coordinator I.