On Saturday, May 4th 6 am-12 pm Facilities will turn off the process steam for the entire building. This will allow contractors to make necessary repairs to the high-pressure steam valve. No process steam will be available to glass washers, autoclaves, and cage washers throughout the building during this time.
News
BJC Institute of Health vertical expansion – Generator load bank testing – April 29th, April 30th & May 2nd
Generator load bank testing will be conducted on BJC Institute of Health generators on April 29th. All testing will be conducted between 10 pm and 2 am. Testing will be conducted Monday, April 29th (10 pm -2 am), Tuesday, April 30th (10 pm -2 am) and Thursday, May 2nd (10 pm-2 am). Testing will be […]
Open flame guidelines
We recently revised the campus-wide guideline for open flames on the OFMD website. For any questions, please contact Michelle Lewis, Director, Administration, Transportation & Parking
Medical Campus street work notification – Clayton Avenue
Sent on behalf of Barnes-Jewish Hospital. Beginning the week of April 29th, Sachs Electric (ArchKey) will be working on the Medical Campus to conduct inner duct pulling activities along Clayton Avenue. Weather permitting, the planned duration of this work is from Monday, April 29th through close of business on Friday, May 10th. All work will […]
Euclid Power Plant work to replace the deaerator (DA) tank starts in June
Starting in June, we are replacing the deaerator (DA) tank at the Euclid Power Plant. On June 22nd and July 27th, we will have a crane set up at this location. During the removal of the old DA tank and the setting of the new DA tank, all access and pedestrian traffic around the area […]
Newstead Avenue street paving
We are pleased to inform you that as part of the Neuroscience Research Building (NRB) project, Newstead Avenue, extending from Clayton Avenue north to the Metrolink tracks, will undergo significant enhancements. This includes milling and paving with new asphalt and re-striping to ensure improved road quality and safety. The work is set to take place […]
Wohl Hospital-Electric Service Interruption 5/11/2024 6 am – 2 pm.
The emergency powered panels from floors 5 through 10 will be deenergized, these panels will experience, (2) power loss episodes during this outage lasting approximately 1 hour. Once at the beginning of the outage and again near the end of the outage. Normal power will not be affected. Those affected will be Receptacles, Cold rooms, […]
Mallinckrodt Institute Radiology-Elevator Service Interruption 5/19/2024
Elevator 103 will be out of service on Sunday, May 19th, at 8 am for 4 hours to perform preventive maintenance. The elevator will be back on service at noon.
Mallinckrodt Institute Radiology-Elevator Service Interruption 5/5/2024
Elevator 102 will be out of service on Sunday, May 5th, at 8 am for 4 hours to perform preventive maintenance. The elevator will be back in service at noon.
McDonnell Pediatric Research Building-Offices 8220A and 8260 A&B Service Interruption 4/26/2024-5/3/2024
8th Floor offices 8220A and 8260 A&B, furniture moving, painting and flooring replacement.