Facilities will be turning off the air handler that feeds the south side of the sixth floor. The unit will be off periodically from 5:00 pm Thursday, February 23rd night to 4:00 am Friday, February 24th morning. During this time the south side of the sixth floor may notice a decrease in airflow and slightly […]
News
Clinical Sciences Research Building-Air Handling Unit Service Interruption 2/22/2023-2/23/2023
Facilities will be turning off the air handler that feeds the north side of the sixth floor. The unit will be off periodically from 5:00 pm Wednesday, February 22nd night to 4:00 am Thursday, February 23rd morning. During this time the north side of the sixth floor may notice a decrease in airflow and slightly […]
Steven & Susan Lipstein BJC Institute of Health-Domestic Cold Water Service Interruption 3/26/2023
On Sunday, March 26th 12 am – 5 am contractors will be adding two valves to the pump skid for future isolation. No domestic cold water will be available for vivarium cage washes and all floors six through eleven during this time.
CANCELLED-Steven & Susan Lipstein BJC Institute of Health-Domestic Cold Water 3/12/2023
On Sunday, March 12th 12 am – 5 am contractors will install two valves and add piping to the domestic cold water system for a new booster pump. No domestic cold water will be available for vivarium cage washes and all floors six through eleven during the above-noted dates and times.
CSRB North Tower Addition-4th Floor Biohazard Area Service Interruption 2/21/2023
On Tuesday, February 21st 5 am – 6 am the horn/strobe alarm notification devices will be tested in the 4th floor biohazard area. No work may occur in the 4th floor biohazard area during this testing.
Mallinckrodt Institute Radiology-Elevator Service Interruption 2/19/2023-3/19/2023
Elevator 103 will be out of service on Sunday, March 19, at 8 am for 4 hours to perform preventive maintenance. The elevator will be back in service at noon.
Mallinckrodt Institute Radiology-Elevator Service Interruption 3/5/2023
Elevator 102 will be out of service on Sunday, March 5, at 8 am for 4 hours to perform preventive maintenance. The elevator will be back on service at noon.
REVISED-Taylor Avenue Building-Elevator Service Interruption 3/13/2023-6/29/2023
Starting Monday, March 13, the TAB Service Elevator (#129) was taken out of service for modernization. The elevator will be out of service for about 20 weeks, returning to service Thursday, June 29th.
Renard Hospital-Hot Water System Service Interruption 3/3/2023
Facilities will be working on the heating hot water system on Friday, March 3rd 12 am – 7 am. The entire building may see cooler-than-normal temperatures.
CANCELED – Genome Data Center-Electric Service Interruption 3/1/2023
Facilities/Contractors will be troubleshooting the West Genome Data Center automatic transfer switch. On March 1st 8 am – 3 pm, there will be switching of breakers to simulate an outage to check the operation of the automatic transfer switch. During this testing we will be single-sourcing US-1 and US-2, we do not anticipate any interruption […]