This outage will affect airflow and temperature regulation on the east side of the building. Lab spaces will have limited temperature control and can be warmer than usual. All fume hoods on the east side of the building will not have flow/exhaust and will be in an audible alarm. Please refrain from using the fume […]
News
CSRB North Tower Addition-HVAC Service Interruption 5/15/2025
On Thursday, May 15th, 3-6 am, the HVAC system supply and exhaust system flows may be reduced to the 4th and 5th floor vivarium and lab spaces to perform preventive maintenance. NO work shall be performed in any BSL3 lab during this time.
Gary C. Werths Siteman Cancer Center-Fire Alarm Service Interruption 5/18/2025
Starting Sunday, May 18th, June 1st, and June 15th. During the time above, facilities along with contractors will be performing tests on the duct detector system of the fire alarm. There will be no alarms or strobes heard or seen during these tests.
Mallinckrodt Institute Radiology-Elevator Service Interruption
Elevator 103 will be out of service on Sunday, May 25th, at 8 am for 4 hours to perform preventive maintenance. It will be back in service at noon.
Steven & Susan Lipstein BJC Institute of Health-BJC-IOH Generators Exhaust Service Interruption
From 7 am on May 19th until 3:30 pm on May 22nd, contractors will work on the exhaust pipes of the BJC-IOH generators and the Wohl Hospital generator exhaust. Each day, the generators will be inoperable from 7 am to 3:30 pm However, they will be closely monitored. In the event of a NORMAL power […]
Clayton Garage-Elevator Service Interruption 5/8-5/12/2025
Thursday, May 8th, 6 pm – May 12th, 4 pm The South elevators, #58 & 59, will be taken out of service to complete some renovation work and move the barricades. Elevator 59 will be returned to service once the work is complete.
Clayton Garage-Elevator Service Interruption 5/8-9/30
Thursday, May 8th, 6 pm through September 30th, 4 pm. Elevator #58 will be out of service for approximately eighteen weeks for modernization.
Southwest Tower-7th Floor Service Interruptions 5/2-3/2025
On May 2nd, 3 pm – May 3rd, 3 pm. To make repairs, freezer 722-A on the 7th floor will be shut down on Friday, 5/2, at 3 pm. Please ensure all temperature-sensitive products are removed from the freezer by that time.
McDonnell Pediatric Research Building-8210 BSL3 Suite Service Interruption 5/7-16/2025
From Wednesday, May 5th, 8 am, to Friday, May 16th, 8 am, the 8210 BSL3 suite will be decontaminated to accommodate maintenance and equipment removal. NO research work may occur in the 8210 suite during this outage.
Steven & Susan Lipstein BJC Institute of Health-Fire Alarm Service Interruption 5/2/2025
On Friday, May 2nd, from 9:30 to 11 am, Barnes facilities, contractors, and the City of St. Louis Fire Alarm Inspectors will test the new system on the fifth floor. Strobes will be visible, and horns will be heard throughout the building. This is only a test; there will be no need for evacuation.