On Friday, May 2nd, from 9:30 to 11 am, Barnes facilities, contractors, and the City of St. Louis Fire Alarm Inspectors will test the new system on the fifth floor. Strobes will be visible, and horns will be heard throughout the building. This is only a test; there will be no need for evacuation.
News
McDonnell Pediatric Research Building-Access Control Programming Service Interruption 5/2/2025
On Friday, May 2nd, 8-9 am, revisions to the access control programming for the 8201 BSL3 suite will be completed. No work may occur in the 8201 BSL3 suite during the outage.
East Building-Elevator Service Interruption 5/2/2025
On Friday, May 2nd 4-6 am both elevators will be out of service for about two hours for work to support the modernization project. Once the work is complete, #47 will be returned to service.
April 30-May 9: Removal of Monitors on the First Floor of BJCIH
Starting April 30th, workers will remove the non-functional frameless monitors on the south wall of the BJCIH lobby on the first floor. The team will frame and paint the opening to match the existing wall. The work should be complete by May 9th. If you have questions, please contact Adam Jones, Engineering Project Manager.
April 29-May 2: Newstead Entrance to Newstead Garage Temporary Interruptions
Due to scheduled construction work, there will be temporary interruptions to the Newstead (west side) entrance and exit of the Newstead Garage from April 29 to May 2. Details of the impact are as follows:• April 29-May 2: There will be no access to the Newstead (west side) entrance and exit of the garage during […]
April 28-May 9: Scott and Euclid Avenues Street Work Notification
Sent on behalf of Barnes-Jewish Hospital. Beginning on April 28th, Archkey started working on the medical campus to conduct WashU Medicine cable pulling activities on the 4500 block of Scott Avenue and the 500 block of South Euclid Avenue. Weather permitting, the planned duration of this work is from April 28th to May 9th.All work […]
Extended – April 9-May 6: Irene Walter Johnson (IWJ) Third-Floor Restrooms Cosmetic Upgrades
Correction: The completion date for this project has been extended to May 6th.From April 9th to May 6th, Interface Construction will cosmetically upgrade the third-floor restrooms in IWJ. This project will convert the men’s restroom to an all-gender restroom, provide cosmetic upgrades, and clean the restrooms. Workers will post signage to indicate which restrooms will […]
Extended – April 7-May 2: McDonnell Sciences Second Floor Men’s Restroom Cosmetic Upgrades
Correction: The completion date for this project has been extended to May 2nd.From Wednesday, April 7th, to May 2nd, Interface Construction will cosmetically upgrade the men’s restroom on the 2nd floor of McDonnell Sciences. This project aims to provide cosmetic upgrades and clean the men’s restroom on the second floor of the McDonnell Medical Sciences […]
Steven & Susan Lipstein BJC Institute of Health-Elevator Service Interruption 4/29-5/1/2025
On Tuesday, April 29th, through Thursday, May 1st, Elevators #111 and #112 will be taken out of service between 3:30 pm and 7:30 pm to complete the 5-year full load testing required by the Elevator Safety Unit of the Missouri Department of Public Safety. Only one elevator will be taken out of service at a […]
Mallinckrodt Institute Radiology-Elevator Service Interruption 4/28-29/2025
Elevator #103 is out of service for repairs until further notice. It will be returned to service once the repairs are complete.