On Thursday, January 30th, from 3 to 7 am, Facilities will shut down the Domestic Hot and Cold water and vacuum to the 7th floor to help assist BJH construction. None of the mentioned utilities will be available during the above-noted times.
Southwest Tower-Domestic Cold Water Service Interruption 1/28/2025
On Tuesday, January 28th, from 3 to 7 am, Facilities will shut down the Domestic Hot and Cold water and the vacuum to the 6th floor to help assist BJH construction. None of the mentioned utilities will be available during the above-noted times.
CSRB North Tower Addition-Exhaust Fan Service Interruption 1/22/2025
UPDATEDAs of 12:45, all systems have been returned to normal, and normal operations may resume. At approximately 10:45 am the exhaust system serving the 4th floor experienced a failure. The backup system worked as expected, returning the room pressures to normal. During the above-noted times facilities technicians will be troubleshooting the cause and making repairs, […]
Mallinckrodt Institute Radiology-Elevator Service Interruption 2/2/2025
Elevator 102 will be out of service on Sunday, February 2nd, at 8 am for 4 hours to perform preventive maintenance. The elevator will be back in service at noon.
CSRB North Tower Addition
On Friday, January 31st, 7 am – 1 pm, DCM is working with a contractor to install new access controls on the 452/462 ABSL3 suite. NO work may occur in this ABSL3 suite during the outage.
CSRB North Tower Addition
On Monday, February 3rd 7 am – 1 pm DCM is working with a contractor to install new access controls on the 434/445 ABSL3 suite. NO work may occur in this ABSL3 suite during the outage.
CSRB North Tower Addition
On February 4th 7 am-1 pm DCM is working with a contractor to install new access controls on the 426/443 ABSL3 suite. NO work may occur in this ABSL3 suite during the outage.
CSRB North Tower Addition
On Wednesday, February 5th 7 am-1 pm DCM is working with a contractor to install new access controls on the 433/444 ABSL3 suite. No work may occur in this ABSL3 suite during the outage.
BJC Institute of Health – Hope Plaza restoration – construction update
The project construction manager BSI Constructors, Inc., began mobilization on site the week of December 23th. While hampered by weather, work in the plaza began the week of January 6th. Initial construction will involve excavating the rock from the planter beds and removing the sidewalk areas within the existing job site fence. Work will also […]
Clinical Sciences Research Building North Tower Addition (CSRB-NTA) ninth-floor link
Workers will start upgrading the elevator lobbies in the CSRB-NTA on Monday, January 20th through May 16th, 2025. The scope includes the area from the door to the CSRB to the expansion joints at the McDonnell Pediatric Research Building. Traffic will be rerouted during the construction for each floor and will take approximately 2 weeks […]