We are pleased to inform you that as part of the Neuroscience Research Building project, Newstead Avenue, extending from Clayton Avenue north to the Metrolink tracks (see map), will undergo significant enhancements. This includes milling and paving with new asphalt and re-striping to ensure improved road quality and safety. The work will occur from April […]
Core@718-Air Handling Unit Service Interruption 4/29-5/3/2024
On April 29th we found a failure for several of the condensing units for the system for the Core@718 building the system will be down for repairs until May 3rd at 4:30 pm. At this time there will be no cooling to the north side of the building on all floors.
Wohl Clinic, McDonnell Medical Sciences Building, Steven & Susan Lipstein BJC Institute of Health-Elevator Service Interruption 5/13-17/2024
Elevators in the listed buildings will be out of service for 2 to 3 hours from 7:00 am to 3:30 pm, between May 13th and May 17th, to complete the 5-year inspections as required by the Elevator Safety Unit of the Missouri Department of Public Safety. The elevators will be selected on a priority basis […]
REVISED-Jeffrey T. Fort Neuroscience Research Building-Steam Service Interruption 5/11/2024
This steam outage is needed to make modifications and repairs to the main steam systems coming into the building. During this outage there will be a minimum amount of heat being generated by our back up heating equipment. All other equipment such as cage washes, autoclaves, sterilizers, and humidifiers will not be functioning. This outage […]
Steven & Susan Lipstein BJC Institute of Health-Steam Service Interruption 5/4/2024
On Saturday, May 4th 6 am-12 pm Facilities will turn off the process steam for the entire building. This will allow contractors to make necessary repairs to the high-pressure steam valve. No process steam will be available to glass washers, autoclaves, and cage washers throughout the building during this time.
BJC Institute of Health vertical expansion – Generator load bank testing – April 29th, April 30th & May 2nd
Generator load bank testing will be conducted on BJC Institute of Health generators on April 29th. All testing will be conducted between 10 pm and 2 am. Testing will be conducted Monday, April 29th (10 pm -2 am), Tuesday, April 30th (10 pm -2 am) and Thursday, May 2nd (10 pm-2 am). Testing will be […]
Open flame guidelines
We recently revised the campus-wide guideline for open flames on the OFMD website. For any questions, please contact Michelle Lewis, Director, Administration, Transportation & Parking
Medical Campus street work notification – Clayton Avenue
Sent on behalf of Barnes-Jewish Hospital. Beginning the week of April 29th, Sachs Electric (ArchKey) will be working on the Medical Campus to conduct inner duct pulling activities along Clayton Avenue. Weather permitting, the planned duration of this work is from Monday, April 29th through close of business on Friday, May 10th. All work will […]
Euclid Power Plant work to replace the deaerator (DA) tank starts in June
Starting in June, we are replacing the deaerator (DA) tank at the Euclid Power Plant. On June 22nd and July 27th, we will have a crane set up at this location. During the removal of the old DA tank and the setting of the new DA tank, all access and pedestrian traffic around the area […]
Newstead Avenue street paving
We are pleased to inform you that as part of the Neuroscience Research Building (NRB) project, Newstead Avenue, extending from Clayton Avenue north to the Metrolink tracks, will undergo significant enhancements. This includes milling and paving with new asphalt and re-striping to ensure improved road quality and safety. The work is set to take place […]