UPDATED-CSRB North Tower Addition-Air Handling Unit 5/17/2023

On Wednesday, May 17-18 8 pm – 12 am Facilities Technicians will be performing preventive maintenance on the air handling and exhaust systems for the 4th and 5th floor. During this time occupants may experience a slight rise in temperatures in the common space areas. To ensure safety all BSL3 labs on the 4th floor […]

McDonnell Pediatric Research Building-Exhaust Fan Service Interruption 5/13-22/2023

To improve the exhaust system and reduce the risk of unplanned failure, Facilities Technicians will replace motors serving the BSL3 suite 8201. To complete this work there will be a series of outages needed. The outages will follow the schedule below. During the times noted there shall be NO work allowed in BSL3 suite 82015/13 […]

Couch Biomedical Research Building-Electric Service Interruption 5/1-5/2023

Facilities and Contractors will be working on running a new power source to the Cold Rooms on the 1st Floor of the Couch building on May 1-5. During this time, work will be performed in the Hallway/Corridor (RM. 1116, RM. 1110, and RM.1101) along with the cold rooms. The power will be off to each […]

Northwest Tower-Elevator Service Interruption 4/30/2023-5/3/2023

The elevators in Northwest tower are operating in emergency dispatch mode until further notice. This means that the elevators will operate continuously, stopping at random floors going up then back down. For example: Going up an elevator may stop at all the odd numbered floors, then coming down it will stop at even numbered floors. […]

Southwest Tower-Fume Hoods Service Interruption 5/6/2023

Facilities will be making repairs to fume hoods that are located on floors six, seven, and eight. No work should be done in the lab area fume hoods on Saturday, May 6th 6 am – 12 pm. The BTCF area will not be affected by this outage.

REVISED – McDonnell Pediatric Research Building, CSRB North Tower Addition, Clinical Sciences Research Building, Wohl Hospital, Wohl Clinic, Renard Hospital, Barnard Hospital-Electric Service Interruption 5/16-19/2023

Facilities Electricians will need to perform switching in the CSR-Substation, which provides power to the above listed buildings. This is to support Ameren de-energizing their equipment for maintenance work. May 16th 6 am – 19th 7 am , the CSRB Substation will be single lined to one utility, instead of the normal two utilities. We […]

Clayton Garage generator project starts Monday, May 8

On Monday, May 8th Clayton Garage generator project will begin with replacing the old generator. We will be blocking off 12 spaces during the project. The north alcove and 6 spaces west of the exhaust stake. This project is projected to carry on through September or early October. We will open up spaces as soon […]