On October 9th from 4 am to 7 am Air handling units 1 and 2 will be down for scheduled cleaning in the Biotechnology Center. In this time there will be limited to no air flow, heating, or cooling to the building.
REVISED-CSRB North Tower Addition-Humidifier Service Interruption 10/10/2024
On Thursday, October 10th 1:30-4:30 Pm maintenance work will be completed on the humidifier of the terminal equipment serving the NTA 452/462 suite. Although facilities do not expect any impact to the performance of the BSL3 lab as a precaution NO work shall take place in the 452/462 lab suite during the above-noted times.
Southwest Tower-Electric Service Interruption 10/14-17/2024
On Monday, October 14th, 17th, 5-7 am, Barnes facilities will be transferring normal power to emergency power to conduct maintenance on their switchgear. The affected floors will be the 6th, 7th, and 8th. There will be a blip during the transfer. There will be three outages: Monday, Tuesday Part B, and Thursday Part B.
Jeffrey T. Fort Neuroscience Research Building-Steam Service Interruption 10/12/2024 6 am – 2:30 pm
To support the steam tie in for the sterilizers on 10th floor construction project all the Autoclaves and sterilizers in the LER hallway floors 3-10 will be out of service. Sorry for any inconvenience this may cause.
Jeffrey T. Fort Neuroscience Research Building-Air Handling Unit Service Interruption 7 am – 3:30 pm
To support the 10th-floor fit-out construction project, we will turn on the heating to the whole 10th floor, EXCLUDING the animal holding rooms, which will maintain normal temperatures. All areas can expect to be warmer than usual on the 10th floor.
McMillan Hospital-Air Handling Unit Service Interruption 10/26/2024
On Saturday, October 26, from 6 am to 2 pm, contractors will turn off air handlers serving floors, lower levels 2, and 9, and sections 3, 4, and 5 to make necessary repairs. During the above-noted dates and times, these areas will experience a loss of airflow and fluctuating temperatures.
McMillan Hospital-Air Handling Unit Service Interruption 10/19/2024
On Saturday, October 19th 7 am – 5 pm contractors will turn off the air handler serving the lower level to make necessary repairs. The lower level will notice fluctuations in temperatures and airflow.
McMillan Hospital-Air Handling Unit Service Interruption 10/13/2024
On Sunday, October 13th, 7 am – 5 pm contractors will turn off the air handler serving the lower level to make necessary repairs. During the above-noted dates and times, the lower level will notice fluctuations in temperatures and airflow.
McMillan Hospital-Air Handling Unit Service Interruption 10/12/2024
Contractors will turn off the air handler serving the lower level to make necessary repairs. During the above-noted dates and times, the lower level will notice fluctuations in temperatures and airflow.
East Building roof replacement update
Workers began the replacement of the East Building’s roof on September 9th. The demolition phase has been completed. The roof replacement is scheduled for October 7th – November 4th, during the hours of 7 am – 5 pm. There will be a series of crane picks throughout the project. All crane picks will occur from […]