Biotechnology Center-Air Handling Unit 10/9/2024

On October 9th from 4 am to 7 am Air handling units 1 and 2 will be down for scheduled cleaning in the Biotechnology Center. In this time there will be limited to no air flow, heating, or cooling to the building.

REVISED-CSRB North Tower Addition-Humidifier Service Interruption 10/10/2024

On Thursday, October 10th 1:30-4:30 Pm maintenance work will be completed on the humidifier of the terminal equipment serving the NTA 452/462 suite. Although facilities do not expect any impact to the performance of the BSL3 lab as a precaution NO work shall take place in the 452/462 lab suite during the above-noted times.

Southwest Tower-Electric Service Interruption 10/14-17/2024

On Monday, October 14th, 17th, 5-7 am, Barnes facilities will be transferring normal power to emergency power to conduct maintenance on their switchgear. The affected floors will be the 6th, 7th, and 8th. There will be a blip during the transfer. There will be three outages: Monday, Tuesday Part B, and Thursday Part B.

McMillan Hospital-Air Handling Unit Service Interruption 10/26/2024

On Saturday, October 26, from 6 am to 2 pm, contractors will turn off air handlers serving floors, lower levels 2, and 9, and sections 3, 4, and 5 to make necessary repairs. During the above-noted dates and times, these areas will experience a loss of airflow and fluctuating temperatures.

East Building roof replacement update

Workers began the replacement of the East Building’s roof on September 9th. The demolition phase has been completed. The roof replacement is scheduled for October 7th – November 4th, during the hours of 7 am – 5 pm. There will be a series of crane picks throughout the project. All crane picks will occur from […]