During July 8th 6 pm – July 25th 4 am the air handler serving the first-floor office area will be shut down to accommodate duct work cleaning. While the air handler is offline, occupants of this first-floor office area will notice warmer than normal temperatures as crews work above the ceiling to access the duct […]
Author: Michelle
Mallinckrodt Institute Radiology, Clayton Garage, Metro Garage, Barnard Hospital, Cancer Research Building, Core@818, Wohl Hospital, Specialized Research Facility East-Elevator Service Interruption 6/24-28/2024
Elevators in these buildings will be out of service for about 2 to 4 hours between 7:00 am and 3:30 pm on June 24th – June 28th, to conduct annual inspections and fire recall tests as required by the Elevator Safety Unit of the Missouri Department of Public Safety. The elevators will be selected on […]
Clayton Garage, Metro Garage, Cancer Research Building-Electric Service Interruption 6/24-26/2024
Elevators in the listed buildings will be out of service to be tested on emergency generator power, from 6 am to 7 am each day, starting on June 24th – June 26th. During this time lighting and equipment connected to the emergency power system may experience a blip when power is transferred. The list that […]
McMillan Hospital-Pressure Monitors in 1103-Anteroom Service Interruption 6/14/2024
On Friday, June 14th 11:00-11:30 am OFMD will be inspecting one of the room pressure monitors in the 1103-Anterooom. NO work may occur in the 1103 BSL3 suite during this inspection.
4480 Clayton-Domestic Cold Water Service Interruption 6/20/2024
On June 20th from 1 am to 6 am there will be no hot or cold water to the 4480 Clayton building for construction on the first floor. In this time there will be no water to restrooms, breakroom sinks, and anything else needing water.
South Medical Building-Cold Room 3912 Service Interruption 6/13-28/2024
On the morning on June 13th there was a failure on Cold room 3912 in the South Medical Building. At this time there can be nothing stored in this Cold room.
East Building, East Imaging Center-Fire Alarm Service Interruption 6/19/2024
On Wednesday, Jun 19th 5-7 am we will be testing the Audio/Visuals for the Fire Alarm System in the East Building and East Imaging. During this test you will hear messages and see strobes, occupants do not need to leave the buildings during this test.
CSRB North Tower Addition-Fire Alarm Service Interruption 6/14/2024
On Friday, June 14th 5-7 am we will be testing the Audio/Visuals for the Fire Alarms system in CSRB North Tower Addition. During this testing you will hear messages and see strobes, occupants do not need to leave the building during this test.
Wohl Clinic-Electric Service Interruption 6/22-23/2024
The Wohl Clinic Emergency Power Generator will be off-line from 5 pm on Saturday, June 22nd, to 5 pm Sunday, June 23rd. Contractors will be replacing/upgrading the emergency power distribution equipment during this time. We do not anticipate any power loss during this time. The generator will be returned to service once all work is […]
Steven & Susan Lipstein BJC Institute of Health-Fire Alarm Service Interruption 6/18/2024
On Tuesday, June 18th 5-7 am they will be further testing of the Fire Alarm system on floors 5 thru 11, there will be speakers and strobes on these floors, and strobes only throughout the rest of the building. There will be no need for evacuation.