Plaza Garage

Sent on behalf of Barnes-Jewish Hospital. Hydrocleaners will be cleaning the Plaza Garage on the weekends of April 1-3 (Green level), April 8-10 (Blue level) and April 15-17 (Red level). Physicians entering from the Euclid entrance will be redirected to the Clayton side of the garage. Normal red parkers being directed to the Duncan Central […]

Barrier walls to be constructed in south lobby

Sent on behalf of Barnes-Jewish Hospital. Starting March 28, Campus Renewal Project contractors will build barrier walls near the gift shop and main level lobby entrance so contractors can perform noise and vibration testing in April. The noise and vibration testing will occur in the early evening to minimize impact. The walls will not block […]

Campus Renewal Update

Sent on behalf of Barnes-Jewish Hospital. During the demolition of Queeny Tower and the construction of the new 16-story inpatient tower at Barnes-Jewish Hospital, BJC and its construction partners have been committed to safety. This recent video features the Campus Renewal team, including BJC infection prevention specialist, Loie Couch, highlighting safety measures established to keep […]

Crane lift on Saturday, March 26th for Newstead and Duncan substation upgrade

Duncan will be closed to through traffic between Boyle and Newstead on Saturday, March 26 at 06:00 am until lift is complete and crane removed. There will be several flatbed trucks that require parking until project is completed. The 4444 east lot located on Newstead will have the center section closed to parking on Saturday, […]

Lift on March 26th to repair roof leaks on FLTC to EPNEC Link

On Saturday, March 26th, there will be a lift to investigate and make repairs on two roof leaks located on the link between Farrell Learning Training Center and Eric P. Newman Center.Please direct any questions or concerns to Antwoine Feaman, Engineering Project Manager.

BJC Institute of Health Vertical Expansion – NW Fire Egress Stair – Change of Condition

On Monday, February 28, Alberici Healthcare, LLC will complete the temporary construction job site fence around Hope Plaza, closing the area to job site use as part of the BJC Institute of Health (BJC IOH) Vertical Expansion Project. Due to the installing of the construction job site fence around the building, we will create a […]

BJC Institute of Health Vertical Expansion – NW Fire Egress Stair – Change of Condition

On Monday, February 28, Alberici Healthcare, LLC will complete the temporary construction job site fence around Hope Plaza, closing the area to job site use as part of the BJC Institute of Health (BJC IOH) Vertical Expansion Project. Due to the installing of the construction job site fence around the building, we will create a […]

West Building dock canopy roof replacement pushed back

The West Building dock canopy roof is being replaced (see green highlight). The work will be done on Saturday, March 12 through Sunday, March 14, during daytime hours to minimize disruption to the south dock. See the area shaded red for the construction zone footprint on the ground (2 dock bays closed during working hours) […]