4/6-9: Cable Removal Along Clayton, Duncan, and Newstead Avenues
Sent on behalf of Barnes-Jewish Hospital. Please be aware that beginning April 6, Kaemmerlen Electric will be working on the Medical Campus to conduct cable removal activities along Clayton Avenue (4200-4500 block), Duncan Avenue (4400 block), and Newstead Avenue (200 block). Weather permitting, the planned duration of this work is from Monday, April 6, through […]
4/9: Planned Service Interruption – Mallinckrodt Institute of Radiology, Fire Alarm
On 4/9 from 3:30 pm to 9:00 pm, Facilities will be testing fire dampers in the building. Airflow may fluctuate during this period.
4/18: Planned Service Interruption – Biotechnology Center, Air Handling Unit
On 4/18 from 6:30 am to 6:30 pm, Air Handler 2, which serves the 1st and 3rd floors, will be shut down to facilitate a contractor installing a new air filtration system. During this outage, there will be no airflow, heating or cooling capabilities
4/8: Planned Service Interruption – 4560 Clayton (Research Building), Building Heat
On 4/8 from 6 am to 11 am, the heating water serving the East Side of the second floor will be valved off to facilitate the contractor’s repair of a leaking pipe. Occupants may notice slightly lower temperatures in the labs and office spaces. Thank you for your patience
4/8: Planned Service Interruption – Fort Labs, Electric
On 4/8 from 8 pm to 4 am, facilities, along with the contractor, will be conducting an electrical outage in order to repair transformer issues for the 10th fl. rooms 10255, 10256, 10257, 10336, 10337, 10356-A, B, C, and D. The 10356 freezer and refrigerator will be affected. The goal is to gain access to […]